Promote the Saemangeum Area as an economic hub city in Northeast Asia.

Construct and develop as a World Free Trade Zone without restrictions to prepare the requirements of the future.

Project History

  • 1975. ~ 1987
    Survey on Southwest Coast Reclamation Resources & Construction Drawing for the External Facility
  • 1989. 11. ~ 1991. 06
    Project Permit Notice(Notice No91-36)
  • 1991. 11. 16
    Start Saemangeum reclamation construction
  • 1991. 11. 28
    No. 1 & 3 Mound break water final closure completed
  • 1994. 07. 25
    No.1 Embankment completed
  • 1998. 12. 30
    Civil-Government Joint Survey
  • 1999. 05. ~ 2000. 06
    Finalize the government sequential eco-friendly development plan
  • 2001. 05. 25
    Fix detailed execution plan according to government policy
  • 2001. 08. 06
    Start Shinsi drainage lockgate electricity construction
  • 2002. 03. 13
    Complete Garyuk drainage lockgate electricity construction
  • 2003. 12. 30
    Successful final connection of 33km embankment
  • 2006. 04. 21
    Reinforcement for the embankment after final Closure
  • 2006. 05.
    Main Process : Heighten embankment road and raising ground level construction
  • 2007.
    Install low ground drainage facility to garyuk, Shinsi
  • 2008. 02
    Internal reclamation land cadastral map drawing
  • 2008. 05
    Cultural Asset Survey for internal reclamation land
  • 2008. 12
    Establish basic plan for internal development
  • 2009. 14
    Saemangeum Development Committee established
  • 2009. 04. 30
    Amendment to the Special Act for Promotion of the Saemangeum Project passed the National Assembly
  • 2009. 07. 23
    Adjustment of Master Plan for Saemangeum Inner Development announced
  • 2010. 01. 28
    Master Plan for Saemangeum Inner Development & Execution Plan reviewed & confirmed (4th Saemangeum Development Committee’s Meeting)
  • 2010. 04. 27
    Construction of the Saemangeum Dike completed
  • 2010. 08. 02
    The Saemangeum Sea (33.9km) Dike listed as the longest manmade sea barrier in the world in Guinness World Records
  • 2010. 11. 15
    The progress of construction reported (Master Development Plan for Saemangeum) (5th Saemangeum Development Committee’s Meeting)
  • 2010. 12. 22
    Public hearing on Master Development Plan for Saemangeum held
  • 2010. 07~ 09
    The construction of seven (7) sea dikes (49.5km) launched
  • 2013. 02. 22
    One area (Area V, 11,513ha) for the development of agricultural land contracted
  • 2012. 10~ 2013
    The construction of two areas (4.7km) of inner dike launched

Project Progress Status

  • After completion of Embankment, Cofferdam ('06.4), greening and road pavement is in progress. Filling the freshwater lake and develop Eco-Friendly Multi-Function Land (420ha)
  • Currently Basic Design is in progress to start Internal Land Development Construction ('09.10).
  • Environment Facilities of Wastewater Treatment Plant, Livestock Manure Treatment Plant, Low area water drainage facility, etc.

Project Effects

  • Secure 379 million ㎥ of Valid Pondage from Saemangeum Freshwater Lake (1 Billion ㎥ Available)
  • Solve habitual inundation problem of 12,000ha farming land at Mangyung River & Dongjin River area.
  • Vast developed tideland provides the most optimum reclamation land – secure 28,300ha of land and 11,800ha of freshwater lake.
  • Improve transportation environment and form integrated tourism area around Gogunsan Ilands, Byunsan Peninsular, and Baekje Cultural Area