Saemangeum Project is to construct a total of 33km of embankment in Gunsan, Gimjae, and the Buan area of Jeollabuk-do to develop 40,100ha of land (Land Development: ,FreshwaterLake:)
사진

Project Area

  • Gunsan: Bieungdo, Naecho, Okgu, Okseo, Hoihyun, Daeya, Okdo (7 Locations)
  • Gimjae: Gwanghwal, juksan, Mangyung, Cheongha, Seungdeuk, Buryang, Jinbonf(7 Locations)
  • Buan: Gyehwa, Dongjin, Haseo, Byunsan(4 Locations)

Project Summary

  • Project Name: Saemangeum Integrated Development Project
  • Project Purpose: To develop as an Economic Hub in Northeast Asia
  • Location: Gunsan City, Ginje City, Buan-gun Area
  • Project Area: 40,100㏊(Land 28,300㏊/Freshwater Lake 11,800㏊)
  • Main Construction: Embankment 33㎞, Drainage Lockgate-2 Locations, Waterproof Bank 125㎞
  • Project Period : Embankment(1991~2009)/Internal Development(2009~2020)

Project Status

  • After the completion of the embankment, Cofferdam ('06.4), greening and road pavement is in progress. Working to fill the freshwater lake and develop eco-friendly multi-functional land (509ha)
  • Currently a basic design is in progress to start internal land development construction ('09.10).
  • Environment facilities of the wastewater treatment plant, livestock manure treatment plant, low area water drainage facilities, etc.

Project Period

  • Total of 30 years between 1991~2020
  • External facility construction between 1991~ 2009
  • Internal development between 2009~ 2020

Project Budget Investment Status (Unit : Billion Won)

Project Budget Investment Status (Unit : Billion Won)
Item Total Budget up to 2007 2008 Plan Accumulated after 2009
Total 41,794 23,286 (56%) 1,798 (4%) 25,084 (60%) 16,710 (40%)
External Facility (Total)
28,642 23,286 (81%) 1,798 (6%) 25,084 (87%) 3,558 (13%)
Embankment 23,946 18,644 1,796 20,440 3,506
Compensation 4,696 4,642 2 4,644 52
Internal Development 13,152 - - - 13,152 (100%)

※ Start construction of the project in 1991, and plan to complete 87% of the external facility 87% by 2008.